The following work was completed:
// New Channel 42 //
- Pouring 10m³ of 300-grade concrete on the channel section.
- Filling joints with bitumen.
- Repairing 4 cavities in the channel using a backhoe, excavating 40m³ and backfilling 60m³.
// BC1-8 Channel, Tell Al-Saman //
The site was leveled and is ready for paving.
// RMS33 Channel, Section 5 //
- Completing the backfilling of the trench adjacent to RMS33 Channel, 75m long.
// Wadi Al-Fayd Channel //
- Continuing the transfer of 100m³ of soil to the break site.
- Spreading the soil in layers with compaction and completing the backfilling work.
- Scraping and leveling the section to prepare it for paving with the required 30m³ of concrete.
// Section 4, Channel 45w //
Two 1600-diameter floats were removed and installed, the base was excavated and replaced with remnants, and 6 1200-diameter floats were lifted.
The canal has been completed, and work on Canal 45w has been finished.
Regarding dredging operations, the following has been completed:
1- Dredging of the Al-Sabahiya drain for a length of 200 meters.
2- Dredging of the Safyan canal for a length of 800 meters.
3- Dredging of the Al-Mahwakiya canal for a length of 600 meters from the Al-Hawija regulator eastward.
Regarding pumping stations, the following work has been completed:
1- Resumption of irrigation according to the required schedules at Pumping Stations 3 West and Al-Yamamah.
2- Removal of the old piling and installation of a new piling for the first pump at the second Al-Wadiyan pumping station, and completion of cleaning work at that station.
3- Maintenance and welding of the discharge pipe for the first group at the Jarwah station.
4- Implementation and application of the irrigation programs required by the irrigation sectors in all projects.
5- Cleaning of the weed screens at all pumping stations to remove vegetation and suspended aquatic debris.